Sunday, March 30, 2008

Plumbing and Slab Prep







This week they did the underground plumbing and prepped for the slab by bringing in a compacting the bedding material. The plumbing went in on March 26 and 27th. Then they filled in and brought in the bedding on Friday the 28th.


Thursday, March 20, 2008

Framed Up And Poured The
Stem Walls On March 19th and 20th.



Tuesday, March 18, 2008



They started digging the footing trenches on Thrusday March 13, 2008. Today (March 18) we went out to take some pictures and found they had poured some concrete into the trenches and placed some rebar.

Monday, March 3, 2008

Roger Getting Ready


Roger Getting Ready For The Pictures Of The Lot.

East Side


Taken From The Road On The East Side Of The Lot

Back East Corner


Taken From the Back East Corner of The Lot Notice The
Elevation Difference Between The Neighboring Lots

Back Of Lot


Back of Lot Looking Toward the Culdesac

Front Of Lot


Front Of Lot Taken From Center of Culdesac